1.0 OBJECTIVE
To lay down the procedure for Operation of Volume Delivering Systems (Peristaltic Pump).2.0 SCOPE
This SOP shall be applicable to Volume Delivering Systems (Peristaltic Pump) in Coating Area.3.0 RESPONSIBILITY
3.1 Execution: Operator3.2 Checking: Production Pharmacist & Above
4.0 ACCOUNTABILITY
HOD-Production / Assigned Designee5.0 PROCEDURE
5.1 PERISTALTIC PUMP
5.1.1 Check the cleanliness of the Peristaltic Pump.5.1.2 Switch “ON” the mains.
5.1.3 Check & set the Peristaltic Pump to required R.P.M. with adjusting knob.
5.1.4 Check for continuous flow of solvent.
5.1.5 After obtaining required R.P.M, check the volume of solution delivered with the help of calibrated measuring cylinder and starts compressed air to spray gun.
5.1.6 Check the spray and start coating as per the procedure.
5.1.7 Switch “OFF” the mains after completion of the operation.
5.1.8 Affix “To Be Cleaned” Label and fill “Equipment Log Book”.
6.0 ABBREVIATIONS
6.1 SOP : Standard Operating Procedure6.2 R.P.M : Revolution Per Minute
6.3 Q.A. : Quality Assurance
6.4 HOD : Head of The Department