1.0 OBJECTIVE
To lay down the procedure for testing of earth pits.2.0 SCOPE
This SOP shall be applicable for all earth pits.3.0 RESPONSIBILITY
Officer/ Executive4.0 ACCOUNTABILITY
HOD engineering5.0 PROCEDURE
5.1 Get all the earth pits, tested through an approved licensed electrical contractor.5.2 Ensure that all readings of the tested earth pits are entered and signed by the approved licensed electrical contractor.
5.3 Add salt and water if reading exceeds 2 Ω.
5.4 Frequency of testing earth pits is once a year.
6.0 ABBREVIATION
6.1 SOP: Standard Operating Procedure