1.0 OBJECTIVE
To describe a procedure for operation of Milli-Q water system from Millipore.2.0 SCOPE
This SOP is applicable for operation of Milli-Q water system from Millipore.3.0 RESPONSIBILITY
Officer/ Executive - Quality Control4.0 ACCOUNTABILITY
Manager - Quality Control5.0 PROCEDURE
5.1 Operating Procedure
5.1.1 Ensure the area is clear.5.1.2 Ensure that water supply is continuing.
5.1.3 Pressure gauge shows the water circulation.
5.1.4 Pressure should be more than 1.5 kg /cm2.
5.1.5 Instrument has three parts.
A. Millipore Elix
B. Millipore Reservoir
C. Millipore Milli-Q
5.1.6 Put on the main switch connected to the system.
5.1.7 Light glows to indicate the power supply to the instrument.
5.1.8 Press operates / stands by mode, displays “pre operate” in Elix.
5.1.9 Water treated in Elix System collect automatically in “reservoir”.
5.1.10 Water again to filter through Milli-Q system.
5.1.11 Press operates / stands by mode, displays “pre operate” in Milli-Q.
5.1.12 Collect Milli-Q water through the outlet.
5.1.13 Press the key stand by display shows “Standby”.
5.1.14 Never put off the power supply to the instrument.
Related: SOP for Cleaning of Water Purification System
6.0 ABBREVIATIONS
6.1 SOP - Standard Operating Procedure6.2 kg - Kilogram
Get ready to use editable documents in MS-Word FormatView List
No comments:
Post a Comment
Please don't spam. Comments having links would not be published.